June 26 (Reuters) - Sweco AB (publ) SWECb.ST :
* IMPROVES LONG-TERM ELECTRICITY SUPPLY THROUGH
REINFORCEMENT OF
NATIONAL GRID IN SWEDEN
* SVENSKA KRAFTNÄT WILL REINFORCE ELECTRICITY GRID IN
CENTRAL
SWEDEN
* HAS BEEN COMMISSIONED TO DESIGN TWO PARALLEL 400 KV
OVERHEAD
POWER LINES TO BE BUILT ALONG A 100-KILOMETRE-LONG SECTION
* WILL DELIVER DETAILED DESIGN OF A NEW DOUBLE OVERHEAD LINE
OF
ABOUT 100 KM BETWEEN TIERP AND SIGTUNA
* WILL DESIGN OF TWO SHORTER OVERHEAD LINE SECTIONS AND
DEMOLITION
OF A 160-KILOMETRE-LONG OVERHEAD LINE
* ASSIGNMENT STARTED MAY 2023 AND WILL CONTINUE UNTIL SEPT
2025
* ORDER VALUE AMOUNTS TO SEK 30 MLN
Source text for Eikon: ID:nWkrc23CNG
Further company coverage: SWECb.ST